Construction work starts on 25MW Energy Works plant

Kick off for Hull bio image

Construction work has started on the 25MW Energy Works energy-from-waste plant in Hull.

M+W Group is the main contractor responsible for engineering, procurement and construction.

Work began in early January on clearing and levelling the 12-acre site, followed by pre-cast driven piling and the perimeter wall demolition on two adjacent brownfield sites near Stoneferry.

Pile driving works were completed in February around the external footprint of the fuel handling building, while more recently, works have also commenced on the installation of sheet piles along the easement wall adjacent to the river.

The site accommodation is also complete and occupied.

Working with M+W Group are two main sub-contractors – Outotec, an international specialist in advanced gasification technology, and Spencer Group, a Hull-based engineering and construction business leading the civil engineering works for the new facility.

Image: impression of the facility (Energy Works)

Tagged in:

Other Tags

Free Trial
X

To receive the next 3 issues of reNEWS complete the form below

 Yes, I would like to receive marketing emails from reNEWS including special offers.


Please leave this field empty.