Chinese land BorWin3 wire work

ZTT turnkey contractor on link between 900MW hub and Hohe See project

Chinese land BorWin3 wire work image

TenneT has contracted Chinese cable manufacturer ZTT to supply and install the 155kV HVAC connection between EnBW’s 497MW Hohe See wind farm and the 900MW BorWin3 grid hub in the German North Sea.

ZTT is the general contractor on the project and will deliver the grid connection on a turnkey basis.

The work also includes the supply of shunt reactors, GIS terminal and land conversion joints.

ZTT has already chosen Van Oord to install the cables and Siemens to provide the shunt reactors.

ZTT executive Tom Qu said: “This marks a significant milestone in our entry and technological contribution to the Europe offshore wind industry.”

TenneT executive Wilfried Breuer said: “We are very pleased to award the contract to ZTT as it increases the number of our suppliers for high voltage cables globally.” 

Image: TenneT

Other Tags

Free Trial
X

To receive the next 3 issues of reNEWS complete the form below

 Yes, I would like to receive marketing emails from reNEWS including special offers.


Please leave this field empty.