Nordsee 1 nears finish line

52 of the 54 Senvion 6.2M-126 turbines installed at 332MW project

Nordsee 1 nears finish line image

MPI Offshore’s jack-up vessel MPI Enterprise has installed 52 of the 54 Senvion 6.2M-126 turbines at the 332MW Nordsee 1 offshore wind farm in the German North Sea.

Turbine installation kicked off in early March this year, and the project delivered first power in the same month.

SSC Wind and REETEC are on the installation job on behalf of Senvion.

All 54 foundation monopiles and transition pieces, as well as the offshore substation, were installed last year.

Water depths at the construction site approximately 40km north of the island of Juist range between 26 and 29 metres.

Full commercial operation of the Innogy and Northland Power-developed wind farm is slated for the end of the year.

Image: Innogy

Other Tags

Free Trial
X

To receive the next 3 issues of reNEWS complete the form below

 Yes, I would like to receive marketing emails from reNEWS including special offers.


Please leave this field empty.