DeepOcean wraps up Race wires

All 91 array cables installed at Dong’s 573MW project off Norfolk coast 

DeepOcean wraps up Race wires image

DeepOcean has completed installation and burial of 91 array cables at Dong Energy’s 573MW Race Bank offshore wind farm off the coast of Norfolk in the UK.

The overall length of the cables was approximately 106km, DeepOcean said.

The work also included route engineering, pre-lay grapnel runs and cable protection system installation.

DeepOcean deployed the Edda Freya, Volantis and Deep Helder vessels and employed its T2 and UT1 trenchers to carry out the work.

Race Bank will consist of 91 Siemens Gamesa 6MW turbines.