Party time at Nordergründe

All 18 Senvion 6.2M126 turbines now connected to the grid

Party time at Nordergründe image

WPD has started full commercial operations at the 111MW Nordergründe offshore wind farm in the German North Sea.

The German developer said the last of the project’s 18 Senvion 6.2M126 turbines were connected to the grid on 17 December. 

The turbines had been installed by the start of December last year. However, commissioning of the project was delayed after substation supplier BVT filed for insolvency in autumn 2016, delaying delivery of the structure.

The remaining substation work was carried out by several sub-contractors, with GE delivering the HV/MV equipment, Muehlhan doing the coating and Stahlbau Nord finalising the steel works.

John Laing Group and the Gothaer Insurance Group are also investors in the wind farm.

Nordergründe managing director Achim Berge Olsen said: “Yesterday was a special day for all of us. We are very happy to have successfully completed the project.”

Image: Senvion

Other Tags

Free Trial
X

To receive the next 3 issues of reNEWS complete the form below

 Yes, I would like to receive marketing emails from reNEWS including special offers.


Please leave this field empty.